Here you will see a small documentation of work proceedings from last few months. This empty and not renovated building became the ’Alt Görlitz’ hotel. We begin first with new photos.
Hotel Alt Görlitz
From 03.05.2010
During last three weeks have been a lot of done. The scaffolding has been removed and the façade is ready. Outside (almost) everything is finished, the eating place is ready to use. On the 01.05.2010 we were celebrating pre-opening. Some of our guests tested our new rooms. There is still to do, and everything is on right way and we are optimistic!
The scaffolding has been removed- a free sight on the facade
also in the back
and eating room
the buffet is waiting
...the party begin....
...and goes on till morning.
The room impressions:




New, from 05.04.2010
Soon will be end: everything dependences from plan; there are a bit backlog; actually, everything manageable, only if you give everything from yourselves.
The boss is also working
Design of the stairway-details
and another detail
New, from 30.03.2010
The façade is getting a becoming shape
The eating room is bricked up and the roof is done.
The roof will be isolated.
after long puttying, finally first compositions of paints
Details from the corridor- it is going to be LOVELY!
New, from 21.03.2010
On the other side the roof is tiled, at the front is still to do 
The windowsills are inbuilt
On the roof the floor will be covered with the stone floor and the decorations form floor will be took off. 
The eating room will be 50 cm higher 
…and because of that must be removed a small part of the old roof
At the ending celebration, there are serious conversations with the architect…
…later, for relax a glass of a good wine
The reception desk will be build- in the morning it looks like that…
...few hours later got a becoming shape…

The round corner for welcome drink is already there
New, from 14.03.2010
the roof tiles are delivered with the crane…
…on the street is very busy.
The tiler is working also on Saturday
Here looks really good!
The new windows are put in!
In the stairway in high gears are preparations for decoration the walls.
The eating room is in progress. 
Our architect is on the track with new ideas
From 06. 03.2010
The investor dared to go on the scaffolding.
The old windows will be knocked down…
…and new ones put in.
On the roof the work is still in progress.
The first tiles covered a wall!
From 27.02.2010

The plasterboards will be delivered…
...and put in right now
The baths are waiting for a tiler
The final plan for eating room has began
The first room decoration is chosen
And we have another we like
From 18.02.2010
The view from 2 weeks.
The appearance from 18.02.2010 -the dormers are on the roof!
The close up view of the dormers. 
The inside view. 
Here looks terrible - but at least the snow is gone!
After covering the floor with the stone floor in baths, the work will be in progress! 
The tiles are already chosen!
The beautiful, old and massive door is burnt off already and is waiting in a dry place for further processing…
Here you can see the door frame in the foreground in original, and in the background already burnt down.
The information technology is from the outset employed.